Problem solution:
A new warp beam storage had to be installed in place of an old building
unit at the centre of the factory grounds. A base frame was installed and levelled on the
newly cast concrete floor slab. It was then possible to place and successively install the
carousel system on this frame with the building crane. When the complete steel structure
had been erected, the hall ceiling and the walls were prepared and the detail installation
work started. This system can be operated from two sides and the upper level is accessible
by foot, where the 18 gear motors and the main part of the carousel mechanics are
located. |